MSD Project Clear Update – January 23, 2020

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

  • DC-02 & DC-03 Relief Sewer Phase 2: Excavation of the tunnel from the bore pit in the northwest corner of Brentwood Park is complete and the pipe has been installed in the tunnel. The contractor has connected the new piping to the piping previously installed during Phase 1 of the project. The work area will be backfilled, which will be followed by restoration of the area disturbed in Brentwood Park. The completion of asphalt paving work is weather dependent and may not occur until Spring.
  • Deer Creek Sanitary Tunnel – The Tunnel Boring Machine excavating the main tunnel is currently excavating beneath the Galleria parking lot and will continue excavating north west until the machine crosses Clayton Road. Tunnel excavation is anticipated to be completed the last week of January.
  • Deer Creek Sanitary Tunnel – The contractor continues excavating a shaft from the surface down to the tunnel at the site near Brazeau and Suburban Tracks. The shaft excavation through the soil is complete. The shaft excavation through the rock, which is being performed using drill and blast methods, will continue for five more weeks.
  • Deer Creek Sanitary Tunnel – The contractor is continuing with drill and blast excavation of the tunnel, which connects the shaft located near Breckenridge Industrial Court and Manchester Road with the main tunnel. This work will continue for several months.

Learn more about Project Clear
Facebook Twitter Email

Other News in Home

State of the City

State of the City

Posted on: January 23, 2020
Brentwood Bulletin Winter 2020

Brentwood Bulletin - Winter 2020

Posted on: April 1, 2019
Winter Weather Tips

Winter Weather Tips

Posted on: December 15, 2019
City Hall Renovation Project

City Hall Closed for Renovations

Posted on: September 2, 2019