News Flash

Home

Posted on: January 27, 2020

Missouri American Water Construction Work

Construction Work

Missouri American Water has contracted with ECM Construction for four water main replacement projects in Brentwood.

The scheduled order for this work:

1. Rosalie Avenue – Start at 8500 Rosalie, then lay pipe southward toward Eulalie Avenue intersection and continue to Black Creek Bridge area.

2. Litzsinger Road – Start on South Hanley Road, then lay pipe westward along Litzsinger Road to a point of connection with Dorothy Avenue.

3. Litzsinger Road – Start on South Brentwood Boulevard, then lay pipe eastward along Litzsinger Road to a point of connection with Dorothy Avenue.

4. Litzsinger Road – Start on Helen Avenue, then lay pipe westward past Mark Twain Elementary to a point of connection with Dorothy Avenue.

The work on Rosalie Avenue is scheduled to begin the week of January 27, 2020.

Facebook Twitter Email

Other News in Home

April Election 2020

General Municipal Election: April 7, 2020

Posted on: February 12, 2020
State of the City

State of the City

Posted on: January 23, 2020
Brentwood Bulletin Winter 2020

Brentwood Bulletin - Winter 2020

Posted on: April 1, 2019
Winter Weather Tips

Winter Weather Tips

Posted on: December 15, 2019
City Hall Renovation Project

City Hall Closed for Renovations

Posted on: September 2, 2019