[ARCHIVED] MSD Project Clear Update – February 13, 2020

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

  • DC-02 & DC-03 Relief Sewer Phase 2: The sewer pipe excavation has been backfilled in Brentwood Park. The CM team and contractor met with representatives from the Brentwood Parks department last week to define the limits of the aggregate surfacing and seeded areas. This restoration work is scheduled to occur over the next three weeks. The completion of asphalt paving work on Bremerton is weather dependent and may not occur until Spring.
  • Deer Creek Sanitary Tunnel – The Tunnel Boring Machine has completed excavating the main tunnel.
  • Deer Creek Sanitary Tunnel – The contractor has interrupted their work excavating a shaft from the surface down to the tunnel at the site near Brazeau and Suburban Tracks to focus on removing the Tunnel Boring Machine and equipment from the tunnel. The shaft excavation through the rock, which is being performed using drill and blast methods, will resume in two weeks.
  • Deer Creek Sanitary Tunnel – The contractor is continuing with drill and blast excavation of the tunnel, which connects the shaft located near Breckenridge Industrial Court and Manchester Road with the main tunnel. This work will continue for several months.

Learn more about Project Clear: https://bit.ly/2zcZyaa 

Facebook Twitter Email

Other News in Home

COVID 19 Resources

Coronavirus (COVID-19) Resources

Posted on: March 5, 2020
COVID-19 Community Updates

Community Updates Related to COVID-19

Posted on: March 19, 2020
Census 2020: Privacy

United States Census 2020

Posted on: February 21, 2020
State of the City

State of the City

Posted on: January 23, 2020
Brentwood Bulletin Winter 2020

Brentwood Bulletin - Winter 2020

Posted on: April 1, 2019