Below is a list of the City of Brentwood’s current and upcoming Capital Improvement Projects. Click on the hyperlinks below to find more information and pictures for each project. Estimated completion dates are subject to change. Check back every few weeks for updated pictures and information.

Current & Upcoming Projects    
Project:
Department Scope of Work
Project  
Start
Estimated 
Completion






           
       
Completed Projects      
Project:
Department
Scope of Work
Facility 
Closure
Estimated 
     Completion
2016 Street Project  Public Works
  • Swan Circle Asphalt Project
  • White Avenue (west of Brentwood Blvd.) Asphalt Project
  • Stratford Lane Asphalt Project
  • Annalee Avenue Asphalt Project
  • White Avenue (east of Brnetwood Blvd)Asphalt Project
  • Rosalie Avenue Asphalt Project
  • Florence Avenue Asphalt Project
  • Brazeau Alley Asphalt Project 
 










July 2016 










July 2016
Litzsinger Road Improvement
 Public Works
Litzsinger Road Project 
August 2015 

 

Spring 2016 
Lutrell Building Demolition
 Public Works
Lutrell Building Demolition 
November 30, 2015

 

Spring 2016 
Veterans Memorial Upgrade Public Works Upgrade to Veterans Memorial Monument at City Hall
August 2015

November 11, 2015
Trail Resurfacing
Parks and Recreation
Trail Resurfacing September 2015
October 2015 
Memorial Park Bench and Shade
Structure

Parks and Recreation
Toddler Playground Bench/Shade Structure
 
September 2015
 
September 2015
Recreation Complex Renovation
 Parks and Recreation
  • Roof Replacement
  • Demolition
  • Community Center Renovation           
  • Ice Arena Renovation       
  • Ice Arena Lobby Renovation         
  • Exterior Renovation       
  • Amenities
 





April 1, 2015

 





September 5, 2015

2015 Street Projects
 Public Works
  • High School Dr Asphalt Project
  • Annalee Avenue Asphalt Project
  • Tilles Dr Asphalt Project
  • Lawn, Pine Ave,(8700 block), Spanish, Urban Dr, Woodsey Dr Asphalt Project
  • Louis Ave Asphalt Project
August 2015
Mid-August 
2015
Oak Tree Playground
Parks &
Recreation
Construction of new playground
July 1, 2014
Nov. 1, 2014
Memorial Park Inline Rink
 Parks &
Recreation

Renovation of existing inline rink
Jan 20, 2014 May 1, 2014


Project Information


 2016 Street Project

2016 Asphalt Street Mill and Overlay Project:
 
July 2016

The 2016 Street Project consisted of the mill and overlay of eight city streets.  The process for each street consisted of two days milling and two days asphalting.
Streets included in the 2016 Street Project were:
  • Swan Circle
  • White Avenue - west of Brentwood Blvd. 
  • Stratford Lane
  • Annalee Avenue
  • White Avenue - east of Brentwood Blvd.
  • Rosalie Avenue
  • Florence Avenue
  • Brazeau Alley  
 

 
   
Rereation Complex Renovation
 

Roof Replacement: November 2014-Februrary 2015 
Updated 5/22/15             
 

The Brentwood Recreation Complex’s 20-year-old roof was replaced in late 2014/early 2015. Leaking and weathered sections of both slanted and flat roofing surface were repaired over the course of 3 months by Shay Roofing Company. The roof over the entire 42,362 square-foot complex had rock removed, overflow drains put in, and new sealant and roofing tiles installed. The roof was replaced one section at a time so patrons and staff were able to use the entire complex throughout the roof replacement process.

Back to Top 

           

Roof Work
   

Demolition: April-May 2015
Updated 6/1/15
 

Destruction of interior walls, flooring, doorways, windows and the Ice Arena refrigeration system and sub-flooring began in early April. This month-long process was crucial for installing updated utility lines and creating new ADA accessible floor plans.

The demolition phase of the renovation is currently complete. 
 
Back to Top

 Room 101
   


Community Center Renovation:
May-Sept. 2015
Updated 8/1/15

The Community Center portion of the Recreation Complex will be renovated to include a larger office space to accommodate staff members, a larger restroom and lobby area, reconfigured multi-purpose rooms, a new kitchen facility, a fitness studio, and complete ADA accessibility. In addition, the concrete sub-floor slab will be replaced, along with the underlying micro-piles to ensure stability of the concrete slab.
          
Utility lines, insulation, and drywall and are now completely installed in the Community Center. Over the next two weeks, contractors will be working on painting walls and ceilings, installing light fixtures, finishing wiring for electrical and fire alarms. By mid-August, flooring, bathroom fixtures and doors will be completed. The last week of August will be used to execute finishing touches, including appliances, furniture, and signage.

Back to Top 

 Room 101
   


Ice Arena Renovation:
May-September 2015
Updated 8/1/15 

Renovation occurring within the Ice Arena will include a new, more sustainable refrigeration system, along with new dasher boards and improved entrance/exit door placement.

The first two weeks of August will include finishing work on the new mechanical systems, placing and leveling sand over the ammonia piping, and installing fabric and insulation layers for the ice surface. At the end of the month, dasher boards, dasher glass, netting and players benches will be set. Rubber flooring will be installed around the rink, a new scoreboard will be installed, and we will begin to make ice.

Back to Top
                                                         

 Ice Rink
   


Ice Arena Lobby Renovation:
May-September 2015
Updated 8/1/15           

Redesign of the Arena Lobby will create complete ADA accessibility, increased locker room size, larger restrooms, a designated Welcome Desk and skate rental area, update office space, improved foot traffic flow, and a reconfigured party room.

Brickwork was completed at the end of July for all enclosed areas in the lobby, including locker rooms, restrooms, a skate room, the front desk and an administrative office. The beginning of August will be dedicated to installing glass windows and walls, framing the ceiling, placing light fixtures and locker room benches. Installing restroom and shower fixtures, completing electrical and fire alarm finishes, laying flooring, and hanging doors and signage will be the focus at the end of August.

Back to Top             
                                                                       

 Rink Lobby
   


Exterior Renovation:
June-September 2015
Updated 8/1/15             

The exterior walls will not be moved or knocked down; however, larger patio space at both entrances will include more plant life, a bigger common area for benches and picnic tables, a designated drop-off area, improved traffic flow, a refinished parking lot, and increased green space within the parking lot.

The majority of the exterior construction will occur within the month of August. First, storefront door systems will be framed, installed and caulked. By mid-August, concrete foundations for the upper and lower patios will be poured, along with a retaining wall and planters. The end of the month will include projects such as curb, gutter and sidewalk work, asphalt paving of the parking lot, landscaping, and sign replacement.
          
Back to Top
                                              

 Exterior
   


Amenities:
August-September 2015
Updated 8/1/15       

New equipment, furniture and facilities are included in the renovation. New multi-purpose room furniture, a demonstration kitchen, and small fitness equipment will be introduced in the Community Center. In the Ice Arena, new bleacher seating, a heating system for patrons, a new score clock, new dasher boards, a new wall mural, and new skates in select sizes will be featured.

Nearly all of these amenities will be installed at the end of August, directly before the Grand Re-Opening Ceremony.

Back to Top

 Exterior Rendering
   
   
Bench and Shade Structure  
Memorial Park: Toddler Playground

Driven by citizen request, this project will give adults a shaded place near the playground to sit and supervise children. Construction will only last week, and the structure will be very similar to the bench/shade components at Oak Tree Playground.
          
Back to Top
 Shade Structure
   
   
Trail Resurfacing  
Brentwood Trail System:
Over 6,000 linear feet of trail will be milled and overlaid with new asphalt. This affects paved trail in Memorial Park, Oak Tree Park, Hanley Park, and the Lee Wynn Trail. The trail resurfacing project is part of the Parks System Master Plan. When the project is complete, all paved trails in Brentwood will have been improved since 2013.
         
Back to Top
Repaved Trail- Memorial Park
   
   
2015 Street Projects  
High School Dr Asphalt Project:  
The City of Brentwood will begin its 2015 Asphalt Project on Lawn Ave., Pine Ave.(8700 block), Spanish Dr., Urban Dr., and Woodsey Dr. starting Friday August 7, 2015. West Contracting will mill the existing asphalt in the subdivision on Friday August 7th, weather permitting. The crew will return on Tuesday August 11th, weather permitting, to apply the new asphalt top. Please be aware of parkingrestrictions along the streets as the project proceeds through the subdivision. 

Back to Top
 High School Asphalt Project - Milling

 
Annalee Avenue Asphalt Project: 
The City of Brentwood will begin its 2015 Asphalt Project on Annalee Ave. between Litzsinger Rd. and Powell Ave. starting Thursday August 6, 2015. West Contracting will mill the existing asphalt on Annalee Ave. on Thursday August 6th. The crew will return on Monday August 10th to apply the new asphalt top. Please be aware of parking restrictions along Annalee Ave. as the project proceeds down Annalee Ave. 

Back to Top
 Annalee - Milling Process
   
Tilles Dr Asphalt Project:
The City of Brentwood will begin its 2015 Asphalt Project on Tilles Dr. between Litzsinger Rd. and McKnight Rd. starting Thursday August 6, 2015. West Contracting will mill the existing asphalt on Tilles Dr. on Thursday August 6th. The crew will return on Monday August 10th to apply the new asphalt top. Please be aware of parking restrictions along Tilles Dr. as the project proceeds down Tilles Dr. 

Back to Top
Tillis - Milling Process
   

Lawn, Pine Ave, (8700 block), Spanish, Urban Dr, Woodsey Dr Asphalt Project:
The City of Brentwood will begin its 2015 Asphalt Project on Lawn Ave., Pine Ave.(8700 block), Spanish Dr., Urban Dr., and Woodsey Dr. starting Friday August 7, 2015. West Contracting will mill the existing asphalt in the subdivision on Friday August 7th, weather permitting. The crew will return on Tuesday August 11th, weather permitting, to apply the new asphalt top. Please be aware of parking restrictions along the streets as the project proceeds through the subdivision. 

Back to Top

Lawn Pine Woodsey Urban Spanish - Milling
   
Louis Ave Asphalt Project:
The City of Brentwood will begin its 2015 Asphalt Project on Louis Ave. between Manchester Rd. and the dead end starting Monday August 10, 2015. West Contracting will mill the existing asphalt on Louis Ave. on Monday, August 10th. The crew will return on Wednesday August 12th to apply the new asphalt top. Please be aware of parking restrictions along Louis Ave. as the project proceeds down the street.  

Back to Top
Louis Ave - Milling
   
   
Veterans Memorial Upgrade  

Veterans Memorial (Corner of Brentwood Boulevard & Eulalie Avenue):
Upgrades have started on the Veterans Memorial at City Hall. Tuck pointing will be completed Thursday August 6. Cleaning and polishing of the plaques, medallions, and eagles are expected to take four to six weeks.

Back to Top 

 Vetetans Memorial - Tuck Pointing completed
   
   
Litzsinger Road Improvement
 


Litzsinger Road Improvement: 
The City of Brentwood Litzsinger Road Improvement project is officially underway. The project includes storm sewer improvements, sidewalk and gutters, mill and overlay, and pedestrian lighting.  This project is 80% federally funded with a 20% local match.
           
Back to Top

Litzsinger - Sewer Work Begins
   
   
Lutrell Building Demolition
 
Lutrell Building Demolition: 
The Lutrell Building Demolition Project is underway.  The building, formerly located at 8318 Manchester Road, has been leveled and land cleanup has begun in order to provide additional green space area within the city. 


Back to Top
 
   

  • Roof Replacement
  • Demolition
  • Community Center Renovation           
  • Ice Arena Renovation       
  • Ice Arena Lobby Renovation         
  • Exterior Renovation       
  • Amenities
  • Roof Replacement
  • Demolition
  • Community Center Renovation           
  • Ice Arena Renovation       
  • Ice Arena Lobby Renovation         
  • Exterior Renovation       
  • Amenities