Brentwood Bound Construction Update – May 12, 2022

Brentwood Bound Construction Update

On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Mass excavation, excavated soils hauling, and soils export
  • Earthwork filling north of the Event Lawn and west of Mary Avenue
  • Landscaping improvements (tentative start)
  • Remaining sheet pile wall installation near Exchange Way (tentative start)

Flood Mitigation Phase 2

  • Pipe-in tunnel boring beneath Manchester Road
  • Bore pit excavation and shoring installation
  • Sheet pile wall installation east of BauserHaus and Breckenridge Material Co.
  • Tree grinding

Deer Creek Greenway Connector Part A

  • Flatwork, curb, gutter and roadway installation 
  • Underground electrical rough-in
  • Permeable paver parking lot construction
  • Trail paving (tentative start)

Event Lawn/Comfort Station 

  • Roof work
  • Ceiling installation and drywall
  • Interior mechanical and electrical rough-in
  • Painting walls
  • Installing Marvin windows
  • Installing underground electrical conduits on west side

MoDOT Manchester Road Improvements

  • Sawcutting, removals, and linear grading
  • Form and pour sidewalks, curb ramps, curbs, gutters, and approaches 
  • Deep sanitary sewer installation and storm sewer improvements
  • Pedestrian underpass demo and shoring
  • Manchester Road closure at Hanley Road
  • Black Creek bridge demolition work
  • Deer Creek bridge improvements

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  

Learn more about Brentwood Bound at www.BrentwoodBound.org.