On April 2, Brentwood voters approved Proposition B, an economic development sales tax to fully fund the Brentwood Bound plan, by a 3-to-1 margin. Here are some next steps:
- Spring/Summer 2019: Brentwood Bound project team continues to acquire the property necessary for the Deer Creek Flood Mitigation project
- Spring/Summer: FEMA reviews Brentwood's application for a Conditional Letter of Map Revision (CLOMR); the City submitted the application in January 2019
- Fall 2019: Board of Aldermen reviews the CLOMR, flood mitigation engineering plans, Manchester Road Improvements plan, and Deer Creek Greenway Connector preliminary design
- Fall 2019: Board of Aldermen considers vote to begin assessing the one-half of one percent economic development sales tax approved by Proposition B