Timeline

Deer Creek Flood Mitigation 

City Property Acquisitions - 7/2018-12/2021

The City will acquire properties needed as part of the construction of the Deer Creek Flood Mitigation project.

Design/Permitting - 8/2018-1/2021

Jacobs Engineering will work on surveying, geotechnical research, wetland research, and design. Throughout the design process, Jacobs will work with key agencies to ensure permitting and approvals are received at the time that the design is completed. 

Demolition Work - 12/2019-7/2021

After the City has acquired the required properties, the City will demolish the applicable buildings and begin preparing the site for construction. The City has completed the phase 1 demolition package, which demolished a portion of the buildings. The City began the second phase in June 2020. The final phase began in February 2021.

Flood Mitigation Construction, Phase 1 - 8/2020-12/2022

Flood mitigation improvements between NEW Brentwood Park (formerly Norm West Park) and Breckenridge Industrial Court

Flood Mitigation Construction, Phase 2 - 7/2021-12/2022

Flood mitigation improvements from Breckenridge Industrial Court to the confluence of Black Creek and Deer Creek

Manchester Road Improvements

Right-of-Way Plans - 5/2018-10/2018

60%-complete drawings are used to determine which properties are needed in order to construct the Manchester Road Improvements design. MoDOT will use these drawings to begin preparing offers and to talk with property owners about purchasing easements or acquiring their property. 

MoDOT Property Acquisitions - 10/2018-3/2021

MoDOT, with the help of its consultants, will approach property owners to acquire easements and properties in order to proceed with the Manchester Road Improvements project in Brentwood. 

Final Drawings - 10/2018-8/2020

While the needed properties are being acquired, TWM (Design Engineer) will complete the drawings and prepare them for permitting and final agency approvals. 

Permitting/Approvals - 4/2020-11/2020

After the final drawings are complete, they will be issued to all governing agencies for permitting and approvals. This includes but is not limited to City of Brentwood, MoDOT, and MSD.

Bidding/Procurement - 4/2021-6/2021

After receiving the permits and approvals from the required agencies, MoDOT will put the project out to bid. This time frame includes bidding, review of bids and final approval of recommended bidder. 

Construction - 8/2021-12/2023

After MoDOT approves the recommended bidder, construction will begin.  

Deer Creek Greenway Connector

Citizen Survey/Community Engagement - 9/2019-11/2019

City Property Acquisitions - 9/2019-12/2021

The City will acquire properties needed as part of the construction of the Deer Creek Greenway Connector.

Design/Permitting - 12/2019-5/2021

Jacobs Engineering will work on surveying, geotechnical research, wetland research, and design for 18 months. Throughout the design process, Jacobs will work with key agencies to ensure permitting and approvals are received at the time that the design is completed.

Demolition Work - 4/2021-10/2021

After the City has acquired the required properties, the City will demolish the applicable buildings and begin preparing the site for construction.

Deer Creek Connector Construction in NEW Brentwood Park - 9/2021-12/2022

After the design is completed, and the permits are received, and the site is prepared, construction will begin.

Deer Creek Connector Construction from Brentwood Boulevard to Russell Avenue - 6/2022-12/2022

After the design is completed, and the permits are received, and the site is prepared, construction will begin.

NEW Brentwood Park (formerly Norm West Park) Projects

Brentwood Park Event Lawn/Comfort Station Building Construction - 9/2021-6/2022

After the design is completed, and the permits are received, and the site is prepared, construction will begin.

Brentwood Park Destination Playground and Natural Water Play Design - 5/2021-1/2022

SWT will work on surveying, geotechnical research, and design. Throughout the design process, SWT will work with key agencies to ensure permitting and approvals are received when the design is completed. SWT will present and review completed design with the Brentwood Board of Aldermen to discuss next steps regarding construction.

NEW Brentwood Park (formerly Norm West Park) Impacts

Norm West Park Public Restrooms/Comfort Station

Closed effective 10/1/2020.

Existing Soccer Field and Dog Park

Closed effective 12/31/2020.

Mary Avenue South of Medical Office Building

Permanently closed effective 12/31/2020.

Executive Walk Apartments

New entrance constructed in Fall 2020.

Road Closures

Mary Avenue South of Manchester Road

Closed to the public effective April 1, 2021. This roadway closure is necessary for L. Keeley Construction to work safely during this construction phase. 

Suburban Tracks Between Brazeau Avenue and Mary Avenue

Closed to the public effective April 1, 2021. This roadway closure is necessary for L. Keeley Construction to work safely during this construction phase. 

Manchester Road at Black Creek Bridge (near Hanley Road) 

Closed 5/1/2022-8/31/2022. 
No lanes will be open. Detour plan to be announced.

Manchester Road at Mary Avenue - Pedestrian Underpass 

Lane reduction 4/1/2022-8/31/2022. 
Manchester Road will be reduced from four lanes to two lanes, with one lane open for each direction of travel. 

Timeline updated 8.19.2021