On April 2, Brentwood voters approved Proposition B, an economic development sales tax to fully fund the Brentwood Bound plan, by a 3-to-1 margin. Here are next steps and updates:
- Spring/Summer 2019: Brentwood Bound project team continues to acquire the property necessary for the Deer Creek Flood Mitigation project
- Spring/Summer: FEMA reviews Brentwood's application for a Conditional Letter of Map Revision (CLOMR); the City submitted the application in January 2019
- August 2019: FEMA issues CLOMR
- Fall 2019: Board of Aldermen reviews flood mitigation engineering plans, Manchester Road Improvements plan, and Deer Creek Greenway Connector preliminary design
- January 1, 2020: Collection of voter-approved Economic Development Sales Tax begins
Follow the progress and updates on www.BrentwoodBound.org