Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- DC-02 & DC-03 Relief Sewer Phase 2: The sewer pipe excavation has been backfilled in Brentwood Park. The restoration work in the park area is being performed. The completion of asphalt paving work on Bremerton is weather dependent and may not occur until Spring.
- Deer Creek Sanitary Tunnel – The contractor has interrupted their work excavating a shaft from the surface down to the tunnel at the site near Brazeau and Suburban Tracks to focus on removing the Tunnel Boring Machine and equipment from the main tunnel. The shaft excavation through the rock, which is being performed using drill and blast methods, is scheduled to resume in late March. The contractor is currently excavating a smaller shaft at this site that will be used to drop ready-mix concrete from the surface down to the tunnel, where it will be transported by locomotives underground and placed in the tunnel liner forms.
- Deer Creek Sanitary Tunnel – The contractor has resumed the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road. This tunnel excavation will continue for several months.
Learn more about Project Clear: https://bit.ly/2zcZyaa