News Flash Home
The original item was published from 6/5/2020 11:13:00 AM to 6/11/2020 10:16:32 AM.

News Flash

Brentwood Bound

Posted on: February 3, 2020

[ARCHIVED] Brentwood Bound Construction Update – June 4, 2020

Brentwood Bound Construction Update

Construction work anticipated in the next few weeks on the Brentwood Bound Plan:

  • Demolition Phase 1B
    • Marschel Wrecking’s subcontractor Bollmeier Plumping is working on water and sewer destroys for 2717 Breckenridge Industrial Drive, 2814 Breckenridge Industrial Drive, 8228 Brentwood Industrial Court, and 8130 Brentwood Industrial Court
    • Marschel Wrecking’s subcontractor AES is working on Asbestos Abatement at 8228 Brentwood Industrial Court and 2717 Breckenridge Industrial Drive
    • Marschel Wrecking is anticipating starting the demolition of the building located at 2717 Breckenridge Industrial Drive on June 15, 2020

Facebook Twitter Email