Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
- Demolition Phase 1B
- Marschel Wrecking’s subcontractor Bollmeier Plumbing is working on water and sewer destroys for 2814 Mary Ave., 2810 Mary Ave. and 2780 Mary Ave.
- Marschel Wrecking’s subcontractor AES is working on asbestos abatement at 8228 Brentwood Industrial Court and 8130 Brentwood Industrial Court.
- Marschel Wrecking anticipates starting the demolition of the building located at 2717 Breckenridge Industrial Drive on July 1, 2020.
- Ameren and Spire will be working on utility disconnects for 8228 Brentwood Industrial Court, 2717 Breckenridge Industrial Drive, 2814 Mary Ave., 2810 Mary Ave. and 2780 Mary Ave.
Flood Mitigation Phase 1
- Project documents will be available for bidding on June 22, 2020.
- Proposals are due July 23, 2020, by 2 pm at Brentwood City Hall.
- The Brentwood Fire Department will conduct training exercises beginning next week at the property located along Mary Avenue.