Brentwood Bound

Posted on: February 3, 2020

[ARCHIVED] Brentwood Bound Construction Update – July 2, 2020

Brentwood Bound Construction Update

Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

  • Demolition Phase 1B
    • Marschel Wrecking’s subcontractor Bollmeier Plumbing will complete the sewer destroys for 2814 Mary Ave., 2810 Mary Ave. and 2780 Mary Ave.
    • Marschel Wrecking’s subcontractor AES will complete the asbestos abatement at 2814 Mary Ave., 2810 Mary Ave. and 2802 Mary Ave. this week.
    • Marschel Wrecking anticipates starting the demolition of the building located at 2717 Breckenridge Industrial Drive on July 13, 2020.
    • Ameren and Spire will be working on utility disconnects for 8228 Brentwood Industrial Court, 2717 Breckenridge Industrial Drive, 2814 Mary Ave., 2810 Mary Ave. and 2780 Mary Ave.
  • Flood Mitigation Phase 1

    • Project documents were made available for bidding on June 22, 2020.
      • Proposals are due July 23, 2020, by 2 pm at Brentwood City Hall.
    • The Brentwood Fire Department will conduct training exercises beginning next week at 8228 and 8130 Brentwood Industrial Drive.