Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- DC-02 & DC-03 Relief Sewer Phase 2: Restoration work is ongoing in Brentwood Park. The completion of asphalt paving work on Bremerton is weather dependent and will be performed this Spring.
- Deer Creek Sanitary Tunnel – The contractor has resumed work excavating a shaft from the surface down to the tunnel at the site near Brazeau and Suburban Tracks. The shaft excavation and excavation of a small diameter chamber from the shaft that connects to the main tunnel is being performed using drill and blast methods. Work will continue at this site until approximately March 27, then there will be short period of inactivity at the site while work is performed at other areas of the project.
- Deer Creek Sanitary Tunnel – The contractor has resumed the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road. This tunnel excavation will continue for several months.
Learn more about Project Clear: https://bit.ly/2zcZyaa