Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- DC-02 & DC-03 Relief Sewer Phase 2: The completion of asphalt paving work on Bremerton is weather dependent and will be performed this Spring.
- Deer Creek Sanitary Tunnel – The contractor has resumed work excavating a shaft from the surface down to the tunnel at the site near Brazeau and Suburban Tracks. The shaft excavation and excavation of a small diameter chamber from the shaft that connects to the main tunnel is being performed using drill and blast methods. The contractor anticipates completing the drill and blast excavation by April 10.
- Deer Creek Sanitary Tunnel – The contractor has resumed the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road. This tunnel excavation will continue for several months.
Learn more about Project Clear: https://bit.ly/2zcZyaa