Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- DC-02 & DC-03 Relief Sewer Phase 2: Sod is being watered in Brentwood Park. The completion of asphalt paving work on Bremerton is scheduled to occur within the next three weeks. The details of the paving work were discussed with representatives of the City of Brentwood on April 16. The schedule for the paving work will be coordinated with the water main relocation work near the intersection of Manchester Road and Bremerton.
- Deer Creek Sanitary Tunnel – The contractor has completed the drill and blast excavation of a shaft from the surface down to the tunnel at the site near Brazeau and Suburban Tracks. No work is anticipated at this site over the next three weeks. The contractor will resume work at this site in mid-May.
- Deer Creek Sanitary Tunnel – The contractor continues the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road. This tunnel excavation will continue for several months.
Learn more about Project Clear: https://bit.ly/2zcZyaa