Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- DC-02 & DC-03 Relief Sewer Phase 2: The asphalt paving work on Bremerton was performed on May 4.
- Deer Creek Sanitary Tunnel – The contractor has completed the drill and blast excavation of a shaft from the surface down to the tunnel at the site near Brazeau and Suburban Tracks. The contractor will begin rearranging the site to accept delivery of the ready-mix concrete that will be used to line the Deer Creek Tunnel.
- Deer Creek Sanitary Tunnel – The contractor continues the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road. This tunnel excavation will continue through June followed by lining the tunnel with pipe.
Learn more about Project Clear: https://bit.ly/2zcZyaa