Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- DC-02 & DC-03 Relief Sewer Phase 2: The asphalt paving work on Bremerton was performed on May 4 and watering of the sod in Brentwood Park was completed this week.
- Deer Creek Sanitary Tunnel – The contractor will continue setting up the site to accept delivery of the ready-mix concrete that will be used to line the Deer Creek Tunnel. Concrete deliveries should begin at this site near the end of the three-week period
- Deer Creek Sanitary Tunnel – The contractor continues the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road. This tunnel excavation will continue through June followed by lining the tunnel with pipe.
Learn more about Project Clear: https://bit.ly/2zcZyaa