Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- Deer Creek Sanitary Tunnel – The contractor has completed setting up the site to accept delivery of the ready-mix concrete that will be used to line the Deer Creek Tunnel. Concrete deliveries should begin at this site at the end of May and continue through the summer.
- Deer Creek Sanitary Tunnel – The contractor continues the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road. This tunnel excavation will continue through June followed by lining the tunnel with pipe.
Learn more about Project Clear: https://bit.ly/2zcZyaa