[ARCHIVED] MSD Project Clear Update – July 30, 2020

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

  • Deer Creek Sanitary Tunnel – The contractor has completed setting up the site to accept delivery of the ready-mix concrete that will be used to line the Deer Creek Tunnel. Concrete deliveries began at this site on June 9 and will continue through the summer.
  • Deer Creek Sanitary Tunnel – The contractor completed the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road on June 24. The contractor is preparing the tunnel for installation of the fiberglass sewer pipe. Pipe installation will begin in early August. Pipe is being stored on the former Midwest Floor site, within a fenced area, until it is installed in the tunnel.

Learn more about Project Clear: https://bit.ly/2zcZyaa

Facebook Twitter Email

Other News in Home

Prop M 2023 disclaimer

Proposition M on the April 4 Ballot

Posted on: February 22, 2023
Message from City

Message from the City of Brentwood

Posted on: March 7, 2023
Brentwood Bulletin Spring 2023

Brentwood Bulletin - Spring 2023

Posted on: January 4, 2023
Connect With Brentwood

Connect with the City of Brentwood

Posted on: February 1, 2023
Subscribe to Enews

Sign Up for Brentwood’s E-Newsletter

Posted on: September 22, 2022
Message from Mayor

A Message from Mayor Dimmitt

Posted on: November 28, 2022
Use Tax Notice

Use Tax

Posted on: November 9, 2021