Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- Deer Creek Sanitary Tunnel – The contractor has completed setting up the site to accept delivery of the ready-mix concrete that will be used to line the Deer Creek Tunnel. Concrete deliveries began at this site on June 9 and will continue through late September.
- Deer Creek Sanitary Tunnel – The contractor completed the drill and blast excavation of the tunnel from the shaft located near Breckenridge Industrial Court and Manchester Road. The contractor is currently installing the fiberglass sewer pipe in the tunnel. Pipe is being stored on the former Midwest Floor site, within a temporarily fenced area, prior to installation. The contractor will begin installing the sheet pile excavation support system for the Diversion Structure at this site later in September.
Learn more about Project Clear: https://bit.ly/2zcZyaa