Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

  • Deer Creek Sanitary Tunnel – The contractor will no longer use the site at the corner of Brazeau and Suburban Tracks to deliver concrete to the tunnel for the final lining of the tunnel. No work is anticipated at this site for the next few weeks. However, the contractor will return to this site later this year to construct the channel and dropshaft that connects the previously installed sewer line to the tunnel.
  • Deer Creek Sanitary Tunnel – The contractor is currently installing the fiberglass sewer pipe in the tunnel. Pipe is being stored on the former Midwest Floor site, within a temporarily fenced area, prior to installation. The contractor will install the sheet pile excavation support system for the Diversion Structure at this site over the next few weeks. 

Learn more about Project Clear: https://bit.ly/2zcZyaa

Facebook Twitter Email

Other News in Home

Cold Weather Resources

Cold Weather Reminders and Resources

Posted on: December 22, 2022
Brentwood Bulletin Winter 2023

Brentwood Bulletin - Winter 2023

Posted on: January 4, 2023
Subscribe to Enews

Sign Up for Brentwood’s E-Newsletter

Posted on: September 22, 2022
Message from Mayor Dimmitt

A Message from Mayor Dimmitt

Posted on: November 28, 2022
Use Tax Notice

Use Tax

Posted on: November 9, 2021