[ARCHIVED] MSD Project Clear Update – June 3, 2021

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

            • Deer Creek Sanitary Tunnel - Brazeau and Suburban Tracks Site – The contractor will excavate to the top of the rock surface for installation of the approach channel. They will begin drilling the existing rock surface to make it easier to excavate and then use a hydraulic breaker to excavate the rock.    
            • Deer Creek Sanitary Tunnel – Manchester and Breckenridge Industrial Site – The contractor will continue constructing the approach channel that connects the Diversion Structure to the pipes that drop flow into the tunnel.

Learn more about Project Clear: https://bit.ly/37XeLOo

Facebook Twitter Email

Other News in Home

Prop M 2023 disclaimer

Proposition M on the April 4 Ballot

Posted on: February 22, 2023
Message from City

Message from the City of Brentwood

Posted on: March 7, 2023
Brentwood Bulletin Spring 2023

Brentwood Bulletin - Spring 2023

Posted on: January 4, 2023
Connect With Brentwood

Connect with the City of Brentwood

Posted on: February 1, 2023
Subscribe to Enews

Sign Up for Brentwood’s E-Newsletter

Posted on: September 22, 2022
Message from Mayor

A Message from Mayor Dimmitt

Posted on: November 28, 2022
Use Tax Notice

Use Tax

Posted on: November 9, 2021