Posted on: July 2, 2020

[ARCHIVED] MSD Project Clear Update – June 17, 2021

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

  • Deer Creek Sanitary Tunnel - Brazeau and Suburban Tracks Site – The contractor has excavated to the top of the rock surface for installation of the approach channel. They will begin drilling the existing rock surface to make it easier to excavate and then use a hydraulic breaker to excavate the rock.    
  • Deer Creek Sanitary Tunnel – Manchester and Breckenridge Industrial Site – The contractor will continue constructing the approach channel that connects the Diversion Structure to the pipes that drop flow into the tunnel. 

Learn more about Project Clear: https://bit.ly/37XeLOo