News Flash Home
The original item was published from 6/24/2021 10:18:00 AM to 7/8/2021 9:09:33 AM.

News Flash

Home

Posted on: July 2, 2020

[ARCHIVED] MSD Project Clear Update – June 24, 2021

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

  • Deer Creek Sanitary Tunnel - Brazeau and Suburban Tracks Site – The contractor has excavated to the top of the rock surface for installation of the approach channel. They have drilled holes in the existing rock surface to make it easier to excavate. They are currently using a hydraulic breaker to excavate the rock.    
  • Deer Creek Sanitary Tunnel – Manchester and Breckenridge Industrial Site – The contractor will continue constructing the approach channel that connects the Diversion Structure to the pipes that drop flow into the tunnel. 

Learn more about Project Clear: https://bit.ly/37XeLOo

Facebook Twitter Email

Other News in Home

Paper Shred Day 2.4.2023

Residential Paper Shredding: February 4

Posted on: February 1, 2023
Cold Weather Resources

Cold Weather Reminders and Resources

Posted on: December 22, 2022
Connect With Brentwood

Connect with the City of Brentwood

Posted on: February 1, 2023
Brentwood Bulletin Winter 2023

Brentwood Bulletin - Winter 2023

Posted on: January 4, 2023
Subscribe to Enews

Sign Up for Brentwood’s E-Newsletter

Posted on: September 22, 2022
Message from Mayor Dimmitt

A Message from Mayor Dimmitt

Posted on: November 28, 2022
Use Tax Notice

Use Tax

Posted on: November 9, 2021