Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- Deer Creek Sanitary Tunnel - Brazeau and Suburban Tracks Site – The contractor will continue to use a hydraulic breaker to excavate the rock at the site in order to install the 60” sewer pipe and the approach channel. Pipe installation may begin during the three-week period.
- Deer Creek Sanitary Tunnel – Manchester and Breckenridge Industrial Site – The contractor will continue to backfill the excavations and install the manhole risers that will be used to access the approach channel. The contractor may begin removing some of the excavation support system as the backfill material is placed.
Learn more about Project Clear: https://bit.ly/37XeLOo