Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- Deer Creek Sanitary Tunnel - Brazeau and Suburban Tracks Site – The contractor has completed using a hydraulic breaker to excavate the rock at the site in order to install the 60” sewer pipe and the approach channel. The 60” pipe installation will begin in early October.
- Deer Creek Sanitary Tunnel – Manchester and Breckenridge Industrial Site – The contractor has backfilled the excavations and will complete removing the excavation support system. Some sitework will be performed, including installation of the electrical ductbank.
Learn more about Project Clear: https://bit.ly/37XeLOo