Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- Deer Creek Sanitary Tunnel - Manchester and Breckenridge Industrial Site – The contractor has finished the majority of the work at this site until Ameren completes the utility pole relocation work being performed for the Brentwood Bound projects. The contractor will then return to complete the electrical work, install the actuator on the control gate, install the precast planks on the Diversion Structure, and install the elevated platform that houses the electrical and control equipment. Anticipate that work will resume at this site in April or May.