Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- Deer Creek Sanitary Tunnel - Manchester and Breckenridge Industrial Site – The contractor has finished the majority of the work at this site. The contractor currently plans to return to the site in late April or early May to install the platform that houses the electrical and control equipment on the diversion structure, and complete the electrical work. There will then be another pause in the work until July, when the actuator for the control gate will arrive and be installed.