Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
- Deer Creek Sanitary Tunnel - Manchester and Breckenridge Industrial Site – The contractor has finished the majority of the work at this site. The contractor has installed the Diversion Structure platform and plans to install the electrical and control equipment on the platform. The contractor will also install the last 25 feet of the underground electrical ductbank installation to the new Ameren power pole at the site. There will then be another pause in the work until later in the summer when the actuator for the control gate will arrive and be installed.