[ARCHIVED] MSD Project Clear Update – October 20, 2022

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

Deer Creek Sanitary Tunnel - Manchester and Breckenridge Industrial Site – Some minor electrical work will be performed at the site this week to prepare for Ameren to potentially install the new electrical service to the site in late October. The remainder of the physical work at the site is currently scheduled to be performed in late November and early December 2022. 