Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:
Deer Creek Sanitary Tunnel - Manchester and Breckenridge Industrial Site – The contractor has removed the existing 54-inch sewer line from within the newly constructed diversion structure and has installed the new slide gate and actuator at the diversion structure. They will be performing the start-up and testing of the gate next week. This will be followed up by installing level sensing instruments in the structure and placing the pre-cast concrete plank cover on the structure. The contractor anticipates that this work will be completed in late December.