Brentwood Bound

Posted on: July 23, 2020

[ARCHIVED] Brentwood Bound Construction Update - July 23, 2020

Brentwood Bound Construction Update

Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

Demolition Phase 1B

  • Marschel Wrecking has mobilized three (3) excavators on site and has started the demolition of the buildings located at 2717 Breckenridge Industrial Drive. They anticipate starting the demolition of 2814 Breckenridge Industrial Drive on July 27, 2020.
  • Spire will be working on utility disconnects for 8228 Brentwood Industrial Court and 2717 Breckenridge Industrial Drive.

Flood Mitigation Phase 1

  • Project documents are available on the City’s website.
    • Proposals are due July 30, 2020, by 2 pm at Brentwood City Hall.
  • The Brentwood Fire Department will conduct training exercises at 8228 and 8130 Brentwood Industrial Drive.
  • The Brentwood Police Department will conduct training exercises at 2714 Breckenridge Industrial Drive.