Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Demolition Phase 1B
- Marschel Wrecking is working on the demolition of the buildings at 8228 and 8130 Brentwood Industrial Drive. They have completed the demolition of the structures and are working on the removal of the concrete slab and foundations.
- Marschel Wrecking will begin the demolition of the buildings at 2780, 2802, 2810 and 2814 Mary Avenue.
Flood Mitigation Phase 1
- L. Keely was issued the contract and the Notice to Proceed for this contract on Tuesday, Sept. 18, 2020.
- L. Keely will begin mobilizing onsite.
Site Camera
See a live view of work on Brentwood Bound through the “Site Cameras” link on the top of the home page of www.BrentwoodBound.org.