Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Demolition Phase 1B
- Marschel Wrecking is working on the demolition of the buildings at 2780, 2802, 2810 and 2814 Mary Avenue. They are projecting that the demolition of these structures will be completed on Friday, Sept. 18.
Flood Mitigation Phase 1
- L. Keely will perform a couple of soil borings along Brentwood Boulevard south of the Metro building and one soil boring next to the Breckenridge Industrial Court bridge.
- L. Keely will begin mobilizing onsite in early October.