Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Demolition Phase 1B
- Marschel Wrecking will be completing the demolition of the buildings at 2780, 2802, 2810 and 2814 Mary Ave. They are projecting that the demolition of these structures will be completed by Friday, Sept. 25.
Flood Mitigation Phase 1
- L. Keely will perform a couple of soil borings along Brentwood Boulevard south of the Metro building and one soil boring next to the Breckenridge Industrial Court bridge.
- L. Keely will begin mobilizing onsite in early October.
Site Camera
See a live view of work on Brentwood Bound through the “Site Cameras” link on the top of the home page of www.BrentwoodBound.org.