Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

Flood Mitigation Phase 1

      • L. Keeley is working on the new Executive Walk Apartments entrance at Brazeau. They are planning on working on the following activities in this area:
        1. Installation of the new Dumpster enclosure
        2. New sidewalk installation
        3. Asphalt pavement
        4. New sign installation
      • L. Keeley is working on the mass grading along Brentwood Industrial Court, removing the overburden from above the location of the new 72” sewer pipe.
      • L. Keeley is installing the temporary gravel roadway for the new intersection of Brentwood Industrial Drive at Breckenridge Industrial Court.
      • L. Keeley will start getting delivery of the 72” sewer piping.