Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Flood Mitigation Phase 1
- L. Keeley is working on the new Executive Walk Apartments entrance at Brazeau. They are planning on working on the following activities in this area:
- Installation of the new Dumpster enclosure
- New sidewalk installation
- Sealing and striping of the parking lot
- New sign installation
- L. Keeley is working on the mass grading along Brentwood Industrial Court, removing the overburden from above the location of the new 72” sewer pipe.
- L. Keeley is installing the temporary gravel roadway for the new intersection of Brentwood Industrial Drive at Breckenridge Industrial Court.
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link on the top of the home page of www.BrentwoodBound.org.