Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Flood Mitigation Phase 1
- L. Keeley is working on the new Executive Walk Apartments entrance at Brazeau. They are planning on working on the following activities in this area:
- Installation of the new Dumpster enclosure gates
- Fine grading and installing seed/straw on all disturbed areas
- L. Keeley is working on the mass grading along Brentwood Industrial Court.
- L. Keeley is receiving delivery of the 72” sewer pipe.
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link on the top of the home page of www.BrentwoodBound.org.