[ARCHIVED] Brentwood Bound Construction Update - May 13, 2021

Brentwood Bound Construction Update

Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

Flood Mitigation Phase 1

  • L. Keeley is working on the installation of the new 72” sewer located behind Life Storage Facility.
  • L. Keeley is working on the installation of the sanitary sewer structures located adjacent to Mary Avenue.

Demolition Phase 1C

  • Marschel Wrecking is demolishing the building at 8734 Suburban Tracks (Brentwood Plastics).
  • Marschel Wrecking will mobilize heavy equipment to 2828/2820 Breckenridge Industrial Ct. for commencing demolition on the buildings (succeeds demolition of 8734 Suburban Tracks). 

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  