Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Flood Mitigation Phase 1
- L. Keeley is working on the installation of the new 72” sewer located behind Life Storage Facility.
- L. Keeley is working on the installation of the sanitary sewer structures located adjacent to Mary Avenue.
Demolition Phase 1C
- Marschel Wrecking is demolishing the building at 8734 Suburban Tracks (Brentwood Plastics).
- Marschel Wrecking will mobilize heavy equipment to 2828/2820 Breckenridge Industrial Ct. for commencing demolition on the buildings (succeeds demolition of 8734 Suburban Tracks).