Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Flood Mitigation Phase 1
- L. Keeley installation of the new 72” sewer
- L. Keeley installation of the new 36” sewer
- L. Keeley installation of sanitary sewer structures located adjacent to Mary Avenue
Demolition Phase 1C
- Marschel Wrecking completion of demolition and site work at 2820|2828 Breckenridge Industrial (Omni|Becker)
- Marschel Wrecking electric, water, and sewer utility disconnects at 2714 Breckenridge Industrial Ct (Midwest Flooring)
- Marschel Wrecking abatement of 2714 Breckenridge Industrial Ct (Midwest Flooring) via AES
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.