Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Flood Mitigation Phase 1
- L. Keeley installation of the new 72” sewer
- L. Keeley installation of sanitary sewer structures located adjacent to Mary Avenue
- L. Keeley soils export
- L. Keeley prep work for bypass pumping of the existing horseshoe sewer
Demolition Phase 1C
- Marschel Wrecking electric utility disconnect at 2714 Breckenridge Industrial Court (Midwest Flooring)
- Marschel Wrecking demolition of 2714 Breckenridge Industrial Court (Midwest Flooring)