Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Flood Mitigation Phase 1
- L. Keeley installation of sewer junction chamber and tie-in of the new 72” FRP sewer
- L. Keeley installation of sanitary sewer structures located adjacent to Mary Avenue
- L. Keeley earthwork for the GRG Connector and Event Lawn/Comfort Station sites
- L. Keeley excavated soils hauling and export
- L. Keeley 24-HR bypass pumping of the existing horseshoe sewer
-
Demolition Phase 1C
- Marschel Wrecking site work (seed, straw, erosion control) at 8000 Manchester Rd (Frederic Roofing)
- Marschel Wrecking completion of punch list work
Deer Creek Greenway Connector Part A
- Ideal Landscaping abatement of 2950 S. Brentwood Blvd. (Brentwood Materials)
- Ideal Landscaping utility disconnects at 2950 S. Brentwood Blvd. (Brentwood Materials)
Event Lawn/Comfort Station
- HOF Construction foundation installation and site utility coordination
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.