[ARCHIVED] Brentwood Bound Construction Update – Sept. 2, 2021

Brentwood Bound Construction Update

Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

Flood Mitigation Phase 1

  • L. Keeley installation of sewer junction chamber and tie-in of the new 72” FRP sewer
  • L. Keeley installation of sanitary sewer structures located adjacent to Mary Avenue
  • L. Keeley earthwork for the GRG Connector and Event Lawn/Comfort Station sites
  • L. Keeley excavated soils hauling and export
  • L. Keeley 24-HR bypass pumping of the existing horseshoe sewer
  •  

Demolition Phase 1C

  • Marschel Wrecking site work (seed, straw, erosion control) at 8000 Manchester Rd (Frederic Roofing)
  • Marschel Wrecking completion of punch list work

 

Deer Creek Greenway Connector Part A

  • Ideal Landscaping abatement of 2950 S. Brentwood Blvd. (Brentwood Materials)
  • Ideal Landscaping utility disconnects at 2950 S. Brentwood Blvd. (Brentwood Materials)

 

Event Lawn/Comfort Station

  • HOF Construction foundation installation and site utility coordination


Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  