Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Flood Mitigation Phase 1
- L. Keeley installation of sanitary sewer structures located adjacent to Mary Avenue
- L. Keeley installation of the 24” sanitary line near Bompart Avenue
- L. Keeley installation of the 36” sanitary line near Mary Avenue
- L. Keeley earthwork for the GRG Connector and Event Lawn/Comfort Station sites
- L. Keeley mass excavation, hauling, and export
Demolition Phase 1C
- Marschel Wrecking site work (seed, straw, erosion control) at 8000 Manchester Road (Frederic Roofing)
- Marschel Wrecking completion of punch list work
Deer Creek Greenway Connector Part A
- Ideal Landscaping mobilization to 2950 S Brentwood Blvd. (Brentwood Materials)
- Ideal Landscaping site fencing and access road install at 2950 S Brentwood Blvd. (Brentwood Materials)
- Ideal Landscaping abatement of 2950 S Brentwood Blvd. (Brentwood Materials)
- Ideal Landscaping utility disconnects at 2950 S Brentwood Blvd. (Brentwood Materials)
Event Lawn/Comfort Station
- HOF Construction mobilization following completion of the Event Lawn site earthwork
- HOF Construction survey and layout for foundations
- HOF Construction excavate for foundations