Construction work anticipated in the next two weeks on the Brentwood Bound Plan:
Flood Mitigation Phase 1
- L. Keeley installation and adjustment of sewer structures located near Mary Avenue
- L. Keeley installation of the 24” sanitary line near Bompart Avenue
- L. Keeley installation of the 36” sanitary line near Mary Avenue
- L. Keeley earthwork for the GRG Connector and Event Lawn/Comfort Station sites
- L. Keeley mass excavation, hauling, and export
- L. Keeley landscaping at the Executive Walk Apartments
Demolition Phase 1C
- Marschel Wrecking site work (seed, straw, erosion control) at 8000 Manchester Road (Frederic Roofing)
- Marschel Wrecking completion of punch list work
Deer Creek Greenway Connector Part A
- Ideal Landscaping site cleanup
- Ideal Landscaping temporary access road install at 2950 S. Brentwood Blvd. (Brentwood Materials)
- Ideal Landscaping abatement of 2950 S. Brentwood Blvd. (Brentwood Materials)
- Ideal Landscaping utility disconnects at 2950 S. Brentwood Blvd. (Brentwood Materials)
Event Lawn/Comfort Station
- HOF Construction survey and layout
- HOF Construction excavate for foundations
- HOF Construction foundations
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.