[ARCHIVED] Brentwood Bound Construction Update – Oct. 7, 2021

Brentwood Bound Construction Update

Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

Flood Mitigation Phase 1

  • L. Keeley installation and adjustment of sewer structures located near Mary Avenue
  • L. Keeley installation of the 36” sanitary line near Mary Avenue
  • L. Keeley earthwork for the GRG Connector, Event Lawn, and Playground sites
  • L. Keeley mass excavation, hauling, and export
  • L. Keeley demolition of the preexisting horseshoe sewer

Flood Mitigation Phase 2

  • L. Keeley site mobilization and staging
  • L. Keeley sheet pile shoring grading and preparation

Deer Creek Greenway Connector Part A

  • Ideal Landscaping abatement of 2950 S. Brentwood Blvd. (Brentwood Materials)
  • Ideal Landscaping utility disconnects at 2950 S. Brentwood Blvd. (Brentwood Materials)

Event Lawn/Comfort Station

  • HOF Construction foundations
  • MEP rough-in below slab

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  

Learn more about Brentwood Bound at www.BrentwoodBound.org.