[ARCHIVED] Brentwood Bound Construction Update – Oct. 21, 2021

Brentwood Bound Construction Update

Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

Flood Mitigation Phase 1

  • L. Keeley installation and adjustment of sewer structures located near Mary Avenue
  • L. Keeley installation of the 36” sanitary line near Mary Avenue
  • L. Keeley earthwork for the GRG Connector, Event Lawn, and Playground sites
  • L. Keeley mass excavation, hauling, and export
  • L. Keeley demolition and abandonment of the preexisting horseshoe sewer

Flood Mitigation Phase 2

  • L. Keeley site surveying
  • L. Keeley clearing and grubbing
  • L. Keeley sheet pile shoring grading and preparation

Deer Creek Greenway Connector Part A

  • Ideal Landscaping utility disconnects at 2948 S. Brentwood Blvd. (Brentwood Materials)
  • Ideal Landscaping demo permitting for 2948 S. Brentwood Blvd. (Brentwood Materials)
  • Ideal Landscaping demo of structures at 2948 S. Brentwood Blvd. (Brentwood Materials)

Event Lawn/Comfort Station

  • HOF Construction pour foundations at Restroom area.
  • HOF Construction place rebar at Event Room areas.
  • Start masonry work at the Restroom area. 

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  

Learn more about Brentwood Bound at www.BrentwoodBound.org.

Facebook Twitter Email

Other News in Brentwood Bound

Brentwood Bound Brentwood Park

Coming in 2023: Brentwood Park

Posted on: January 4, 2023
Brentwood Bound Pedestrian Tunnel

Coming in 2023: Pedestrian Tunnel

Posted on: January 4, 2023
Playground Groundbreaking 11.3.22

Destination Playground Groundbreaking

Posted on: November 3, 2022