[ARCHIVED] Brentwood Bound Construction Update – December 9, 2021

Brentwood Bound Construction Update

Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

Flood Mitigation Phase 1

  • L. Keeley 36” sanitary sewer installation near Mary Avenue and adjustment of sewer structures.
  • L. Keeley mass excavation of the creek bank and the large pond area near Mary Avenue.
  • L. Keeley excavated soils hauling and export.
  • L. Keeley earthwork filling for the playground area.
  • L. Keeley partial creek restoration.

Flood Mitigation Phase 2

  • L. Keeley construction staking and layout for upcoming waterline bore and overhead powerline relocation.
  • G&S waterline bore beneath Deer Creek near Breckenridge Industrial Court (on behalf of Missouri American Water).
  • Ameren construction staking, layout, and tree trimming for upcoming overhead powerline relocation.

Deer Creek Greenway Connector Part A

  • Ideal Landscaping sewer and water disconnects at 2948|2950 S. Brentwood Blvd.
  • Ideal Landscaping demo permitting for 2948 S. Brentwood Blvd.
  • Ideal Landscaping storm sewer installation.
  • Ideal Landscaping retaining wall installation.

Event Lawn/Comfort Station

  • HOF Construction MEP wall and under slab rough-in activities at the event room area.
  • HOF timber framing and masonry wall construction at the restroom and event room areas.