[ARCHIVED] Brentwood Bound Construction Update – January 13, 2022

Brentwood Bound Construction Update

Construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Sanitary sewer installation near Mary Avenue and adjustment of sewer structures
  • Mass excavation of the creek bank
  • Excavated soils hauling and export
  • Earthwork filling for the North Event Lawn
  • Partial creek restoration
  • Walking trail prep and installation

Flood Mitigation Phase 2

  • Prep and boring pit excavation for the 72” sanitary sewer installation
  • Waterline bore beneath Deer Creek near Breckenridge Industrial Court 
  • Overhead powerline relocation 

Deer Creek Greenway Connector Part A

  • Demo permitting for 2948 S. Brentwood Blvd.
  • Storm sewer installation
  • Retaining wall installation

Event Lawn/Comfort Station

  • Timber frame roof sheathing
  • Under slab water and waste piping and backfill in the event space area
  • Under slab water piping and backfill in the north restrooms
  • Topping out masonry walls to roof deck

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  

Learn more about Brentwood Bound at www.BrentwoodBound.org.

Facebook Twitter Email

Other News in Brentwood Bound

Brentwood Park Grand Opening

Now Open: Brentwood Park

Posted on: January 4, 2023
Brentwood Bound Pedestrian Tunnel

Opening Soon: Pedestrian Tunnel

Posted on: January 4, 2023