Construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Complete installation of the top slab for the Diversion Structure near Mary Avenue
- Adjustment of sewer structures
- Sewer improvements
- Mass excavation, excavated soils hauling, and soils export
- Earthwork filling north of the Event Lawn
- Completion of the sheet pile wall installation south of Deer Creek
Flood Mitigation Phase 2
- Bore pit excavation and rock breaking for the pipe-in tunnel beneath Manchester Road
- Slide rail shoring system installation
- Pipe-in tunnel boring beneath Manchester Road
- Overhead powerline relocation
Deer Creek Greenway Connector Part A
- Pavement and hardscape demolition
- Demo of structures at 2948 S. Brentwood Blvd.
- Storm sewer installation
- Haul road installation
Event Lawn/Comfort Station Roof
- Roof plywood installation
- Roofing installation
- Steel stud exterior wall framing
- Above slab MEP rough-in
- Fireplace gas line install
MoDOT Manchester Road Improvements
- Sawcutting and removals
- Form and pour sidewalks, curb ramps, curbs, gutters and approaches
- Deep sanitary sewer installation
- Electrical rough-in
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.