On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Mass excavation, excavated soils hauling, and soils export
- Earthwork filling and soil stockpiling for the playground
- Landscaping improvements
- Remaining sheet pile wall installation near Exchange Way (tentative start)
Flood Mitigation Phase 2
- Exit bore pit excavation and shoring installation
- Large sanitary sewer piping installation
- Sheet pile wall installations east of BauserHaus and Breckenridge Material Co. (tentative start)
Deer Creek Greenway Connector Part A
- Flatwork, curb, gutter and roadway installation
- Site electrical rough-in
- Permeable paver parking lot construction (tentative start)
- Trail paving (tentative start)
Event Lawn/Comfort Station
- Taping drywall
- Installing Nana walls
- Installing windows, exterior wood siding and stone
- Finishing underground electrical service conduits
- Laying out the water service line
MoDOT Manchester Road Improvements
- Sawcutting, removals, and linear grading
- Form and pour sidewalks, curb ramps, curbs, gutters, and approaches
- Deep sanitary sewer installation and storm sewer improvements
- Light pole base installation
- Pedestrian underpass construction
- Manchester Road closure at Hanley Road
- Black Creek bridge construction
- Deer Creek bridge improvements (on Manchester Road west of S. Brentwood Blvd.)
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.